Speed up the progress of bidding packages for peeling off organic soil layers on the Hanoi - Hai Phong expressway
24/05/2009
The organic soil removal bidding package, collectively known as BHC, includes 8 bidding packages from BHC 1 to BHC 10 (except for 2 construction and installation insurance bidding packages EX7 & EX9). Currently, the implementation status of BHC packages for expressway motorways is as follows: BHC package 1: total length is 6.2km (from km 0+000 to Km 6+200). Currently, the bidding package is being accelerated for site clearance to begin construction. BHC package 1: total length is 6.2km (from km 0+000 to Km 6+200). Currently, the bidding package is being accelerated for site clearance to begin construction. According to the plan, by April 15, 2009, there will be about 2.5km to 3km of the first route.
BHC 2 bidding package:Total length of 12.8km, from Km 6+200 to Km 19+000 (Cuu Cao, Long Hung, Tan Tien communes of Van Giang district; Hoan Long, Yen Phu, Viet Cuong, Minh Chau communes of Yen My district - Hung Yen Province). Currently, the bidding package has about 10.4km of land and is under construction. 9.7km of embankment has been built; Organic peeling for the main road is 4.9km; Peeling off organic soil for the public service road is 3.1km; Embankment of main road is 600m; Embankment of public service road is 1.5km.
BHC Package 3:Total length of 14km, from Km 19+000 to Km 33+000 (Minh Chau, Ly Thuong Kiet, Tan Viet communes, and Yen My town of Yen My district; Xuan Truc, Van Du, Dao Duong, Tan Phuc, Bai Say communes of An Thi district - Hung Yen Province). About 12km has land; build a 10km embankment; Organic peeling is 5.82km; Build the roadbed for about 500m to 600m.
BHC Package 4:Total length of 15km from route Km 33+000 to Km 48+000 (Thai Duong, Thai Hoa, Tan Hong, Thuc Khang, Binh Minh, Thai Hoc, Nhan Quyen, Co Bi communes in Binh Giang district; Yet Kieu, Gia Hoa, Le Loi, Phuong Hung communes in Gia Loc district - Hai Duong province); There is about 12.8km of land available; Organic peeling is about 11.6km; Covering more than 500m.
BHC 5 bidding package:Total length of 15.3km from route Km 48+000 to Km 63+300 (Phuong Hung commune, Gia Loc, Gia Khanh, Hoang Dieu towns of Gia Loc district; Ngoc Ky, Hung Dao, Tai Son, Quang Phuc, Binh Lang, Dong Ky, Tan Ky communes of Tu Ky district - Hai Duong province); There is about 11.5km of land available; About 9.61 km of the main road has been organically removed; Organically peeled 2km of public service roads; Cover about 1.3km.
BHC Package 6:Total length 8.7km (Km 63+300 to Km 72+000); Currently, there is no construction site. By January 31, 2009, 2km of construction site was handed over to the contractor.

BHC 8 bidding package:Total length of 10km from route Km 81+300 to Km 91+300 (My Duc and An Thai communes in An Lao district; Thuan Thien, Huu Bang and Dai Duong communes in Kien Thuy district - Hai Phong city); 8.17km of land is available; Organic peeling is 1.54km; Covering about 600m3.
BHC 8 bidding package:Total length of 10km from route Km 81+300 to Km 91+300 (My Duc and An Thai communes in An Lao district; Thuan Thien, Huu Bang and Dai Duong communes in Kien Thuy district - Hai Phong city); 8.17km of land is available; Organic peeling is 1.54km; Covering about 600m3.
BHC 10 bidding package:Total length of 9.1km from route Km 96+300 to Km 105+400 (Hoa Nghia and Hai Thanh wards of Duong Kinh district; Trang Cat, Nam Hai and Dong Hai wards of Hai An district - Hai Phong city); About 5km of site has been handed over, about 2km of construction has been implemented; Since April 1, 2009, backfill pumping has been carried out.
Construction units, investors, and investors are trying to speed up the progress of bidding packages, ensuring the completion of the road as planned.