In June 2012, site clearance of the Hanoi - Hai Phong expressway project was completed
Leaders of Hai Phong City People's Committee have just had an inspection to resolve problems and difficulties in site clearance work for the Hanoi - Hai Phong expressway project.
Photo Vidifi.,jsc
Currently, site clearance work on the entire route is 98% complete, with only a small area remaining in An Lao district and Duong Kinh district.
Chairman of City People's Committee. Hai Phong highly appreciates the efforts of localities and assigned sectors. At the same time, localities are requested to continue urgently implementing and completing site clearance in June 2012. For some remaining land areas because people refuse to relocate, request An Lao district and Duong Kinh district, City. Hai Phong is ready to make a enforcement plan and make it public to the people, for the overall success of the entire project.
During implementation, it is necessary to firmly adhere to the law and create maximum conditions for people. For residential buildings, irrigation systems, and schools affected by pile foundation construction, the investor is required to coordinate closely with the contractor, assess the level of damage, and provide adequate compensation. The investor and localities coordinate closely to immediately resolve problems in site clearance as well as during the construction process.
According to Transport Newspaper