Complete the design and estimates of main construction and installation packages for the Hanoi - Hai Phong expressway
18/12/2009
To date, the main construction and installation packages of the Hanoi - Hai Phong Expressway Project have completed their designs and estimates.
6/10 main construction and installation packages have been approved and their estimates have been verified; The Institute of Economics - Ministry of Construction is urgently verifying the estimates of the remaining packages.
6/7 auxiliary bidding packages have also completed design; Particularly, the bidding package for Toll Stations, Service Stations and Operators has not been completed due to the need to adjust the vertical alignment of some sections and some intersections.
The technical design verification of the entire project was assigned by the Investor to the Korea Expressway Company (KEC).

Hoang Giang